4th Year Project 6 Working Draws: Waweru L.N

1 .FLOOR FINISHES.
a. 600mmx600mmx30mm granito tiles on 1:4 mortar mix, laid on lime mortar
screed.
b. 6 mm thick epoxy polished terrazzo laid on lime mortar screed,50% glass and marble
chops, to architects approval.
c. 300x300 x10mm thick glazed ceramic tiles.
d. Approved 12.7mm x 120mm x 1200mm stained and sealed mahogany flooring
planks inlaid with brushed aluminium strips laid with adhesive on 20mm 1:4 lime
sand screed.
e. 25mm thick cut mazeras stone tile on lime mortar screed.
f. 40mm screed smooth finish.
g. 150mm x 45mm x 1200mm mpingo wood floor plank decking.
2.WALL FINISHES.
a. 12mm thick lime wash coat on lime plaster, treated with waterproofing
admixture. Coats applied to manufacturers' specifications.
b. Exposed machine cut coral stone.
c. 450mm x 300mm x 20mm thick glazed ceramic tiles 1200mm high with 10mm
straight continuous joints in both directions fixed with adhesive on faux
exposed concrete render background with grouting to approval.
d. Coral lime plaster finish containing egg white (3 coats).
e. 75mm x 25mm mpingo wood planks nailed on masonry wall.
f. Emulsion paint.
3.SKIRTING FINISHES.
a. 45mm x 100mm thick ceramic tiles.
b. ex.75mm x 25mm thick mpingo strips nailed on wall.
c. 100mm x 25mm dressed coral stone pieces on 16mm plaster.
d. Random cut and stacked mazeras stones.
4.CEILING FINISHES.
a. 9mm first coat 1:4 lime/sand screed and 3mm second coat of lime plaster,
smooth trowelled on structural slab.
b. Painted waterproofed rough cast lime finish
c. Mpingo timber strips nailed on timber joists
d. 25mm thick suspended gypsum ceiling board and plaster on lime soffit
e. 150mm x 100mm boriti poles alternate with gypsum board.
f. 600mm x 600mm x 10mm Armstrong acoustic ceiling tile with reflective foil on
one side

EDULE
NOTES
GENERAL
1. Drawings not to be scaled. Only figured dimensions to be used.
2. All dimensions are shown in mm unless otherwise stated.
3. P.V. denotes permanent vent.
CIVIL WORKS.
1. All slabs at ground level to be poured over 1000 gauge polythene sheeting
on 50-75mm coral screed on 50-100mm hardcore.
2. All soils under slab to be treated for termite control.
3. All soils on cut embarkments to be stabilised.
STRUCTURAL WORKS.
1. Depth of foundation to be determined on site to S.E's approval.
2. For all Coral aggregate reinforcement works refer to S.E details.
3. All adjascent Coral aggregate reinforcement works and masonry walls to
be tied with strap wrought iron at every course.
4. All walls less than 200mm thick to be reinforced with hoop wrought iron at
every alternate course.
MECHANICAL.
1. All plumbing and drainage to comply with Lamu County Council
specifications.
2. All service ducts to be accesible from all floors.
3. SVP denotes soil vent pipe to be provided at at the head of drainage
4. Drains passing beneath buildings and walkways to be encased in 150mm
concrete surround.
5. All underground foul and waste drain pipes to be class 41 golden brown
pvc pipe
6. Minimum slope in the drain to be 1%
ELECTRICAL.
1. All conduits must be laid before plastering

Documentation : 
AttachmentSize
WD COMPILATION.pdf6.29 MB

Calendar

M T W T F S S
 
 
1
 
2
 
3
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
11
 
12
 
13
 
14
 
15
 
16
 
17
 
18
 
19
 
20
 
21
 
22
 
23
 
24
 
25
 
26
 
27
 
28
 
29
 
30